SERVICE · INDUSTRIAL

Industrial 3-phase installations.

New supplies, properly sized, DNO handled.

New 3-phase supplies, capacity upgrades, sub-mains and load assessments for factories, warehouses and process plant. Where DNO liaison is required, we handle it.

 

A BRIEF INTRODUCTION

Why 3-phase installs go wrong.

Industrial 3-phase installs fail in two places. Either the supply was undersized for the actual load – and now the building’s been throttling itself for years – or the install was technically right but the DNO liaison wasn’t handled, and the new connection’s been waiting six months for paperwork.

We do 3-phase installs properly. That starts with measuring the existing load (not estimating it from nameplates), modelling what the new equipment will draw, calculating supply requirements with appropriate headroom, and either lodging a DNO supply increase or sub-billing within the existing supply where capacity allows.

New supplies, properly sized, DNO handled. The 3-phase installations done right is the 3-phase installations that doesn’t come back as a problem in two years.

The DNO piece is where most contractors fall down. Electricity North West (the DNO for most of Lancashire) has lead times of 4-8 weeks for new connections or supply increases, and the application paperwork is exacting. We do this part of the job as standard – you don’t need to deal with the DNO yourself.

On the install side it’s a job like any other – properly sized cables, proper containment, proper labelling, proper testing. We sub-out the DNO connection itself (only the DNO can connect to their network) but everything inside the building boundary is our work.

WHAT'S INCLUDED

Every 3-phase installations job includes all of this, as standard.

01

Existing demand measurement.

We measure actual current demand over a representative period – not estimate from nameplates. Real numbers, not theoretical maximums.

02

Supply sizing with headroom.

Calculation based on existing demand plus new load plus appropriate headroom. We size for the future, not just the install spec.

03

DNO application and liaison.

Where new connection or supply increase is needed we lodge the DNO application and manage the process. Lead times 4-8 weeks typical.

04

Sub-main installation.

Cables sized correctly, properly contained, labelled at both ends. SWA where appropriate for buried runs, glanded where it leaves the building.

05

Distribution board and metering.

Where new supplies feed new distribution we install the board, set up sub-billing if required, and label every circuit.

06

Testing and major works certification.

All new supplies tested per BS 7671. Major works electrical installation certificate issued before commissioning.

THE PROCESS

How a typical install actually works.

DAY 1 · SURVEY
Site visit and load measurement.
We install a current measurement logger on the existing incomer for a week to get accurate demand data. Concurrent assessment of new load requirements.
01
DAY 1 · SURVEY
DAYS 7-10 · ANALYSIS
Load report and recommendations.

Logged data analysed against new load requirement. Report covers existing demand profile, new load impact, recommended supply size, DNO involvement if required.

02
DAYS 7-10 · ANALYSIS
DAY 11-12 · QUOTE
Written quote with timeline.
Quote covers cable and containment install, distribution board if needed, DNO application costs, testing and certification. Honest timeline including DNO lead time.
03
DAY 11-12 · QUOTE
PRE-INSTALL · DNO
Application and liaison.

Where DNO uplift required we lodge the application immediately and manage the process. Typical 4-8 week lead time before energisation can be scheduled.

04
PRE-INSTALL · DNO
INSTALL · 1-5 DAYS
Cable, containment, board, testing.

Internal install proceeds during DNO lead time. Sub-main installed, distribution board commissioned, ready for DNO energisation on agreed date.

05
INSTALL · 1-5 DAYS
SIGN-OFF · SAME DAY
Energisation and certification.

DNO energises the new supply, we commission the internal install, test every circuit, issue the EIC and update all schedules.

06
SIGN-OFF · SAME DAY

TYPICAL FIGURES

What an average 3-phase install typically involves.

Figures from new 3-phase supply work across East Lancashire industrial sites over the past twelve months.
 

SUPPLY SIZE TYPICAL

200 A

Most common 3-phase capacity for SME manufacturing

DNO LEAD TIME

6 wk

Average lead time for Electricity North West supply uplift

INTERNAL INSTALL

3 day

Cable, containment, board and testing time

ENERGISATION

1 day

Final DNO connection and commissioning

TYPICAL FIGURES

Questions we get a lot.

Internal work is 3-5 days. DNO lead time (where applicable) adds 4-8 weeks. We start internal install during DNO lead time so the wait is parallel rather than sequential.

Depends on existing capacity vs new demand. If your incomer can take the extra load, we sub-board within the existing supply. If it can’t, the DNO needs to increase your incoming capacity.

The client. DNO fees vary widely (£500 to £15,000+) depending on the upgrade needed. We get the formal DNO quote on your behalf as part of the project.

Yes – single-phase loads can be balanced across the three phases. We design the distribution to balance the phases so no single phase is overloaded.

Yes – where the new supply is for a sub-tenant or a separate department needing cost recovery, we install sub-meters and configure them for billing.

Then we install a new distribution board off the new supply, leaving your existing distribution for existing loads. Common arrangement for factory expansions.